LETTER TO THE EDITOR: Nixon Roof Estimate is Higher

Sudbury Public Schools Committee Vice Chair Lisa Gutch says the updated estimate is $38,000 more than previously reported.

Several weeks ago, an estimate of $750,000 for Article 1, Roof Replacement and Repair - Nixon Elementary School, was submitted for the Sept. 24 Special Town Meeting Official Warrant. 

Since the time that the Warrant was published, the architect who has been assigned to Sudbury by the Massachusetts School Building Authority has completed an initial design for the roof. 

This week, with the completion of this design work, we were given an updated estimate that is $38,000 higher than the estimate provided for the Town Warrant. 

Find out what's happening in Sudburywith free, real-time updates from Patch.

The estimate that will be presented at the Special Town Meeting on Monday is $788,000.  

Respectfully,

Find out what's happening in Sudburywith free, real-time updates from Patch.

Lisa Gutch Vice Chair

Sudbury School Committee 


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here